China Tower Shandong, Heze City Branch Development Zone Wanda Plaza New Tower Project


Project Name: China Tower Shandong Branch Heze Branch2024 New Tower Project, Building 11, North District, Wanda Plaza, Development Zone

Construction site: North District of Wanda Plaza, Economic and Technological Development Zone, Heze City, Shandong ProvinceBuilding 11

Floor space (square meters):50

Construction unit:China Tower Co., Ltd. Heze Branch

Legal Representative: Han Qiujian

Contact: Wang Peiliang

Project investment (ten thousand yuan):2.95

Environmental protection investment (ten thousand yuan):0.5

Proposed date of production and operation:2024-03-12

Construction nature: new

Filing basis: The project belongs to the construction project that should fill in the environmental impact registration form in the "Classification Management Directory of Environmental Impact Assessment of Construction Projects", and belongs to the No.166 all of the wireless communication items.

Construction content and scale

Project Code:24A01SDHZ011000266

Address code:371703900010001748

Construction location:115.46946,35.22234

Construction content:

Tower: New3 pay wall holding pole

Machine room: new outdoor cabinet

Supporting: newly added integrated power supply (2 modules), add 1 set of lithium batteries, addMoving ring monitoring, new power-off sensor mains: attached17 meters, 125 meters of old pipeline

Mobile to be installed:2G system, transmitting frequency range uplink 890MHZ-909MHZ/downlink 935MHZ-954HZ ZTE wireless equipment, nominal power 160W, actual transmitting power 40W,3 antennas, antenna gain 16.5dBi;4G system, transmitting frequency range 1885MHZ-1915MHZ/2575MHZ-2635MHZ, ZTE wireless equipment, nominal power 160W, actual transmitting power 40W,3 pairs, gain antenna frequency range 75MHZ, MHZ, MHZ, system, nominal power 240W, actual transmit power 120W,3 antennas, antenna gain 24.5dBi.

Proposed installation of Unicom:3G system, transmission frequency range 1940MHZ-1955MHZ/2130MHZ-2145MHZ, ZTE wireless equipment, nominal power 60W, actual transmission power 20W,3 antennas, antenna gain 17dBi;4G system, transmission frequency range 1755MHZ-1765MHZ/1850MHZ-1860MHZ,904MHZ ~ 915MHZ/960MHZ; ZTE antenna, actual power, antenna, antenna, power 17 dBG, the transmission frequency range is 3400MHZ-3600MHZ (jointly built with telecom), ZTE wireless equipment, nominal power 200W, actual transmission power 53W,3 antennas, antenna gain 25dBi.

Telecom to be installed:LTE800 system, transmitting frequency range 790MHZ-960MHZ, Huawei wireless equipment, nominal power 40W, actual transmitting power 15W,3 antennas, antenna gain 16dBi;LTE1800 system, transmitting frequency range 1710MHZ-2690MHZ, Huawei wireless equipment, nominal power 40W, actual transmitting power 15W,3 antennas, antenna gain 18dBi.

Electromagnetic radiation:

  1. controlling the transmitting power of the antenna and optimizing the transmitting angle of the antenna;
  2. After the base station is completed, electromagnetic radiation environment detection shall be carried out on sensitive points as required, and the detection value shall meet the "Electromagnetic Environment Control Limit" (GB8702-2014 public exposure control limit requirements specified in).
  3. Waste lead-acid batteries and comprehensive scrap materials are handed over to units with corresponding disposal qualifications for disposal.

Commitment:China Tower Co., Ltd. Heze BranchHan Qiujian promises that the contents filled in are true, accurate and complete, and the construction project complies with the provisions of the "Administrative Measures for the Filing of the Environmental Impact Registration Form of Construction Projects. If there is fraud, concealment, deception, etc. and all the consequences arising therefrom.China Tower Co., Ltd. Heze BranchHan Qiujian takes full responsibility.

Receipt of filing: the environmental impact registration form of the project has been filed

Record No:20243717000100000014。

Successful Cases